Del Mar Club  Five Year Plan

 

  The following items are proposed for repair and replacement of amenities and common areas to improve community appearance and continue to add to property value; project completion times will vary.   If you are aware or items or have suggestions for improvement, please send them to us by clicking here 

 

  • Landscaping Design

    • choose new landscaping company - complete 2017

    • review and approve landscaping design - planned 2017

    • review and repair irrigation by section - completed 2017

    • removal of dead trees and foliage - ongoing 2017 - 2018

    • Implement landscaping design for entrances - on going - beds updated 5/2018

    • Implement landscaping design for clubhouse and other areas - planned 2018-2019

    • Refresh Landscaping Shrubs /color - Review Start 2020

    • Replace with Straw with Mulch  - 2020

  • Clubhouse repairs

    • repair or replace flooring - completed 2018

    • install storage  - on hold

    • repair inside ceiling fans - completed 2017

    • repair exterior ceiling fans - completed 2017

    • repair internal lighting -  completed 2017

    • repair of columns patio - completed 2017

    • security system/cameras - completed 2019

  • Playground

    • replace playground- completed 2017

    • add trash receptacle -completed 2017

    • refresh pine mulch - yearly spring/fall

    • review health of trees on the playground - 2018 (with landscaper)

    • removal of trees as needed

  • Tennis Court

    • request proposals for repair of turf - 2017

    • implement repairs of turf - planned  2019 need additional proposals

    • add access control - complete 2017

    • repair of windscreens - ongoing as needed

  • Sidewalks

    • review  and proposals - on hold (will revisit in 2021)

    • installation and additional review - 2019-2021

  • Pool

    • choose a new pool vendor - completed 2017

    • repair of lighting and pumps - complete 2017

    • repair of showers - completed 2017

    • pressure washing of deck and walk area -  on going as needed

    • review proposal for additional  pool furniture - review 2019

    • purchase pool furniture - proposed 2019

    • purchase and install pool covers - completed 2017

  •  Fencing

    • review proposal for full replacement fencing  -  2019-2021

    • review proposals for partial replacement - 2018 - 2019 (on hold)

    • review proposals to repair and paint  - 2019 (on hold)

    • Fence replacement - 2020-2021

Long Term Projects (spanning more than two years)

 

  • Review proposed plans for empty lots Mare pond - 2020

    • approve Plan - planned -2022

    • Implementation of Plan  for longer-term projects- 2022

  • Entrance Enhancements

    • Repair Replace signage on monuments - 2019 - 2020

    • Repair replace entrance lighting  - partial 2019 (complete), 2020

    • Upgrade Power at monuments  - 2020- 2021

 